A chemical & tire group: large-scale SCADA and machine-networked MES

One is an ocean of variables and alarms; the other a scale battlefield of equipment networking — practices across two extreme scenarios in the process industries.

A Taiwan-invested chemical company (two phases of a Bisphenol A unit) and a tire group (all-steel / semi-steel curing plants) — corresponding to the process industries' two extreme scenarios: alarm governance and equipment networking.

Customer background

A Taiwan-invested chemical company (two phases of a Bisphenol A unit) and a tire group (all-steel / semi-steel curing plants) — two extreme scenarios in the process industries: one an ocean of variables and alarms, the other a scale battlefield of equipment networking.

Challenges

  • Chemical units have thousands of variables and alarm floods; real anomalies are buried, and the risk of misoperation is high
  • Tire curing is the lifeline of quality; OEM audits require every mold and every cycle's full-process curves traceable
  • Hundreds of curing presses networked on the same segment — address planning and data consolidation are heavy engineering
  • Continuous production allows no data gaps — process curves from outage periods must be recoverable

Our solution

The solution covers two scenario types: alarm engineering governance for large-scale chemical SCADA, and scale and reliability evidence for the curing-press-networked MES:

  • Chemical SCADA · unit-level centralized monitoring with nearly 80,000 variables / 24,000+ alarm points (temperature control loops / tank farm & dock / energy / alarms)
  • Chemical SCADA · standardized governance with alarm manager + event list + reset list — alarms are not "popped up" but "managed"
  • Tire MES · phase one covers 366 curing presses: curing press → pit PLC → group-control SCADA → MES four-tier link
  • Tire MES · 40+ collection points, real-time values on a 6-second cycle; three-needle process curves retained in full at 14,400 rows per machine per day
  • Tire MES · barcode ↔ left/right mold ↔ bladder ↔ three-needle curve forward/backward traceability
  • Tire MES · full MES functions (plan / execution / material / traceability / process / quality / equipment / reports) + ERP/PLM/WMS/high-bay warehouse/HR interfaces, with standardized data interface specification delivered
  • Tire MES · outage backfill collection written into the technical agreement and accepted: after a communication outage is resolved, curing curves from the interruption period are automatically backfilled
  • Tire MES · redundant clusters, 7×24 operation, three-year data retention, second-level screen refresh

Results

  • Chemical unit alarms standardized; alarm fatigue and missed-alarm risk significantly reduced
  • Traceability moved from 1–2 days of record search to minute-level queries; scrap and recall scope narrowed precisely to a single mold and single cycle
  • The solution has a replication record across multiple group sites (including migration to next-generation PLC platforms); template reuse reduces repeated design, while specific delivery timelines and costs must be calculated per site boundaries

Technology stack

SCADA configuration softwareMitsubishi PLC (including the iQ-R new platform)SQL Server clusterOracle/ERP interfacesRedundant cluster architecture

Project boundaries and replication conditions

  • Project boundaries:The implemented scope covers the Bisphenol A unit SCADA; machine-networked MES for Plant A/B semi-steel curing areas, outage backfill collection, traceability and enterprise system interfaces, and group site replication
  • Applicability conditions:Large-scale I/O, continuous processes or machine-fleet networking; stable point lists / curve protocols and clear network zoning
  • Replication prerequisites:Before replication, confirm point lists / curve protocols, network zoning, master-data associations and the group's unified interface templates
  • Not disclosed:Scale figures confirmed by responsible persons must not be presented as technical agreement text; traceability time improvements, scrap or recall benefits may only be described qualitatively

Related Industry Solutions

Confirm whether this project's boundaries apply to your site

Tell us about your industry and site conditions to get a diagnosis and phased solution proposal.

Request an On-site Diagnosis